Project Timeline

Project Timeline:

New Single Mode Fiber Infrastructure – June 2013-July 2015

Consolidation of switches, removal of older switches and reduction of active ports (from 25000 to 8000) – June 2015-August 2015

Convert from 13 core distribution points to 7 – June 2015-August 2015

Move from a flat Layer-2 to a Layer 3 distributed network – December 2015-August 2016

DNS,DHCP and other IP resassignment work – December 2015-August 2016