Project Timeline:
New Single Mode Fiber Infrastructure – June 2013-July 2015
Consolidation of switches, removal of older switches and reduction of active ports (from 25000 to 8000) – June 2015-August 2015
Convert from 13 core distribution points to 7 – June 2015-August 2015
Move from a flat Layer-2 to a Layer 3 distributed network – December 2015-August 2016
DNS,DHCP and other IP resassignment work – December 2015-August 2016